2010-Jan-16 - Wooroloo - Internal Cladding # 8
While I completed the cut outs for the lighting switches on the garage wall, Kaj finished the fastening of the upper sheet on the bathroom wall.

We then went on to complete the lining on the other side of this wall and between the bathroom and the garage.

Whenever I was installing insulationl, Kaj was completing work on the door headers.


Cut out for light switch in garage area


First bathroom wall before lining


First bathroom wall (shared with laundry)


Second bathroom wall before lining


Half lined


Upper sheet tacked in place