2018-Jul-28 - Wooroloo - Windows #27
This was pretty much a repeat of last week, except with better weather - no rain - just cloudy.

It was still pretty hard work hoiking a 40 Kg beam in and out of position and drilling holes through a 6mm PFC.

I had two beams to finish.

It took me about 3 hours for the third beam and 2 hours for the fourth beam.

This was followed by removing last week's tarpaulin and reinstalling the temporary siding.

My automatic welding helmet seems to be failing - I need to repair a broken headband and adjust the transmission level - it was quite hard to see the joints that I was welding.

Next week I will start installing the cross purlins necessary to pick up the ends of floorboards where the bay window structure intervenes.

I need to drill and fold some brackets during the week.


All beams installed and fixed