2021-Mar-27 - Wooroloo - Back Wall #57
It has taken me forever to prime the next two sets of back wall doors.

I finally have them ready and out on site.

I want to take a few days away from the cladding the side wall.

This is because I want to get Peter on to installing them as soon as possible - I am concerned that he will become unavailable in the Perth house building boom we are currently experiencing.

To this end I need to install the door stops in each frame and roughly place the door pairs.

This usually involves me skimming about 5mm off each door.

Peter will finesse this even more as he mounts the doors on their hinges and adjusts them to the best fit possible.

I had hoped to set up both sets - but it took me all day just for one.

It is amazing how heavy a door frame with 8 panes in it is.

By the end of the day I was exhausted.


Progress by the end of the day