To make up for the lost Saturday I spent some time out on site today.
I was up at 5.00 am and started work on site at 7.00 am.
I spent about an hour cutting a number of sheets to fit the diagonal and fastening everything down.
I then worked through to 12.30 pm progressing about two thirds down the garage door side of the building.
By now it was becoming very hot on top of the galvanised iron sheeting especially with the sun directly overhead and no shade available.
I had a shower and headed home to do some work for my clients.