2012-Dec-28 - Wooroloo - Steelworks #62
I have taken two weeks off during the Christmas / New Year break.

The first week went on socialising and it wasn't until Friday 28th that I had my first chance to get back to installing purlins.

I had quite a number that have been pulled out and washed and I wanted to install these to get them out of the way.

The weather has been very hot and this has made progress difficult.

On one occasion I was only able to last up to midday before having to stop.

I worked Friday, Saturday, Monday, Tuesday and Thursday.

On the alternating days Linda and I have been catching up with the movies that are currently showing.

I will do one more day on purlins this coming Saturday and then I need to start working on the street level superstructure.


Purlins installed so far