The electricians are waiting for me to install the ceiling before they sign off on their work.
Out of ignorance, I had not expected that - I had hoped to be tiling the wet area by now.
The first job in the morning was to carry in some second hand gyprock sheets that I had been storing outside under cover.
We completed a number of other jobs in the earlier part of the day.
In the afternoon I put Peter to work on installing some light angle iron on the east side.
This is needed for the gyprock to fasten at the edges.
I can see that this is going to be a big job - probably 12 weekends
I'm doing some research in to buying a sheet lifter to make the work easier and quicker.