2020-Sep-22 - Wooroloo - Back Wall #48
Pretty much the same work as Friday.

I managed 3 architrave positions on Saturday and the last 3 on Sunday.

On Monday I nipped out to site to perform a little bit of cleaning up and to fetch back the architraves (it was raining on Sunday evening).

On Tuesday I applied primer to the architraves.

On Wednesday I applied the first coat of cottage cream to the cladding

On Friday I applied the first coat of enamel to the architraves.


Progress by the end of Sunday

Architraves primed

First coat on cladding